First phase of South Elementary School's project completed

Published 10:24 am, Thursday, August 21, 2014
  • The upper level glass blocks at South Elementary School in New Canaan, Conn., have been removed and replaced with weather-proof boards as part of a window replacement project. Phase one of the project was completed Aug. 8, 2014, and phase two is scheduled to begin in summer 2015. Photo: Nelson Oliveira / New Canaan News
    The upper level glass blocks at South Elementary School in New Canaan, Conn., have been removed and replaced with weather-proof boards as part of a window replacement project. Phase one of the project was completed Aug. 8, 2014, and phase two is scheduled to begin in summer 2015. Photo: Nelson Oliveira

 

Larger | Smaller
Email This
Font
Page 1 of 1

The first part of a $2.6 million window replacement project at New Canaan's South Elementary School has been "successfully completed," Nancy Harris, the district's interim director of finance and operations, told the Board of Education Monday.

Split into two phases, the project will repair or replace some of the windows, replace a failing glass block structure in the upper level of the school and repair the building expansion joint. The glass block structure will be replaced with frosted glass, according to Harris.

Phase one, which lasted about a month and cost $411,700, included the removal of the glass block and abatement of hazardous materials from non-teaching spaces.

The area is now sealed up with weatherproof boards until the second phase, which includes more abatement and the replacement of the windows, begins in summer 2015.

At Monday's meeting, Harris praised the work of Niram, the New Jersey construction company in charge of phase one.

"They were on time, they were neat, they were thorough," she told the board.

Harris said environmental experts and engineers visited the construction site every day "to make sure all containment remained intact" and "that all materials were removed properly."

The finance director said the building committee overseeing the project plans to launch the bidding process for phase two in the fall.

The committee's next meeting is Thursday, Aug. 28, at 10 a.m. in room 102 at South.